Excavation starts for Melbourne Metro Parkville station

Excavation works has started for the underground Parkville Station as part of Melbourne Metro Tunnel project. The crews are digging the 270-metre long and 30-metre-wide station box around 30 metres below Grattan Street, between Leicester Street and Royal Parade.
Excavators will initially dig around 3 metres deep, while a temporary deck made of concrete and steel is simultaneously built at surface level to reduce noise and dust impacts. Digging will continue once the deck is completed by March, with trucks heading underground via a ramp to remove rock and soil from beneath the deck.
“Significant work is ramping up at the site of the new Parkville Station, as we get on with the job of delivering the world-class train network and state-of-the-art stations that Victoria deserves,” Victorian Acting Premier, James Merlino said.
Digging will continue once the deck is completed by March, with trucks heading underground via a ramp to remove rock and soil from beneath the deck.
Once the excavation reaches around 15 metres it will be too deep for trucks to enter, so gantry cranes will be used to lower buckets through holes in the deck to collect rock and soil. The cranes will then lower excavated material into trucks inside two acoustic enclosures at surface level, before the trucks exit the site.
The first of three massive gantry cranes have already been installed over the site. The 20-metre high cranes will help remove up to 35 tonnes of rock and soil at a time from beneath the deck and lower construction equipment and materials into the excavated space. All three cranes will be installed by the end of February 2019.
Excavation will continue until the end of this year, with around 200,000 cubic metres of rock and soil to be removed from the site in 2019. Once complete, station construction and fit-out will continue underground.
The construction is well underway on all five Metro Tunnel stations – the new North Melbourne (near Arden Street), Parkville, State Library, Town Hall and Anzac.
The Metro Tunnel project is a year ahead of schedule, with the first train set to run through the tunnel in 2025.


Share on:
Facebooktwitterlinkedinmail

 

RECOMMENDED EVENT: