London’s Charing Cross and Waterloo East stations will be completely closed for 22 days, from July 26 to August 16, to modernize the rail infrastructure between them. Trains operated by Southeastern will be rerouted to other stations in central London, and passengers are advised to expect delays and cancellations.
Two of the most important stations in central London will be without trains for three weeks as part of a modernization project estimated at GBP 20 million.
No trains will stop at London Charing Cross and Waterloo East from July 26 through August 16. The closure will affect services operated by Southeastern, the company that provides connections between London and southeastern England.
Trains that normally arrive at Charing Cross will be rerouted to London Victoria, Cannon Street, and Blackfriars, and some will terminate at London Bridge.
Passengers are urged to check their route before traveling, as schedules and terminal stations will be modified for the duration of the work.
1.8 km of track and 16 new turnouts
Network Rail, the UK’s rail infrastructure manager, will replace approximately 1,800 meters of track on the section between Charing Cross and Waterloo East.
The project also includes the installation of 16 new turnouts, equipment that allows trains to switch from one track to another.
The existing infrastructure dates back to 1990, and its replacement should reduce the number of breakdowns and improve service reliability in one of the busiest areas of the London network.
At Waterloo East, the track drainage system will also be modernized. The work is necessary to maintain track alignment and ensure that trains can run safely at normal speeds.
Work on the platforms at Charing Cross
Part of Charing Cross station will be rebuilt during the closure.
At the end of the platforms facing the exit from central London, the foundations and passenger areas will be rebuilt. Network Rail states that these improvements are necessary to maintain the station’s safety and accessibility.
Crews will also work on nearby railway structures, including the Hungerford Bridge, which carries the tracks across the Thames and is approximately 175 years old.
Structural repairs are also scheduled for the footbridge connecting Waterloo East station to the London Waterloo complex. The infrastructure manager states that the work will extend the structures’ service life by several decades.
Southeastern Trains Diverted to Other Stations
During the 22-day closure, Southeastern services will have altered routes and terminals.
Some trains will be rerouted to Victoria, Cannon Street, and Blackfriars, while others will terminate at London Bridge. The operator warns that there will also be cancellations, and some trips will take longer.
Affected passengers will be able to request refunds for all eligible ticket types. Southeastern will make a dedicated form available starting July 26.
Refunds will also cover situations where passengers were forced to use alternative routes deemed reasonable.
Six Additional Days of Closures
In addition to the main closure period, there will be several weekend closures to prepare for and complete the work.
Service will be affected on July 18 and 19, prior to the main construction period, as well as on the weekends of August 22–23 and October 10–11.
Network Rail warns that service arrangements on these days may differ from those in effect during the 22-day closure.
The alternative would have been 60 weekends with restrictions
Southeastern and Network Rail say they chose a complete closure to reduce the total duration of the disruptions.
According to the operator, the same work would have required either approximately 60 weekend closures or four or five separate periods, each lasting nine days.
“By concentrating the work into a 22-day closure, supported by preparation and completion weekends, we can finish faster and with fewer disruptions than with the alternative options,” said Scott Brightwell, director of rail services at Southeastern.
The period was chosen during summer vacation, when schools are closed and ridership is approximately 20% lower than during the rest of the year.
Normal service through Charing Cross and Waterloo East is scheduled to resume on Monday, August 17, after the main work is completed.