CFR SA will publish two tenders under the air-rail link project

The two tenders envisage the selection of a consultant, as well as the selection of the constructor for design and execution services for the modernisation of Bucuresti Nord (Bucharest Central Station)-Bucharest Henri Coanda International Airport Railway.
The first of the two tenders to be published refers to contracting design and execution works for the investment objective “Modernisation of Bucuresti Nord-Bucharest Henri Coanda International Airport railway, Phase I: Rail Link terminal T1, Bucharest Henri Coanda International Airport.
The tender is estimated at RON 497.38 million (EUR 106.6 million), VAT excluded.
The deadline for receiving the expression of interest is 24 December 2018 and the launch of the attribution procedures is expected in the same day.
According to estimates, the contract notice will be published on 24 December 2018.
The project is financed through the Large Infrastructure Operational Programme – POIM.
The attribution criterion will be the best quality – price ratio. For the same attribution criterion, the technical proposal will weigh 60%, while the bid price will have a share of 40%.
CFR SA estimates that the duration of the contract will be 14 months for design and execution works of which 2 months for the design and 12 months for the execution. The warranty period will be of 60 months.
According to the description of the project, the constructor to be selected will have to provide works according to the investment objective consisting of the design and execution of works in conformity with the legislation and the technical regulations in force. Under the contract, railway infrastructures and superstructure works will be executed, as well as structure works, civil engineering works, architecture, resistance works and railway signalling and telecommunications works. Execution technologies will consider all conditioning imposed by notifications and to observe the duration of the contract.
The second tender consists of contracting consultancy and supervision services for the design and execution of works for the investment objective mentioned above.
This tender is estimated at RON 6.96 million (EUR 214.000).
Some requirements are similar to those included in the design and execution tender, so that the deadline for receiving the expression of interest is 24 December 2018 and the beginning of the attribution procedures is expected in the same day.
According to estimates, the contract notice will be published on 24 December 2018.
The project is financed through the Large Infrastructure Operational Programme.
The attribution criterion will be the best quality – price ratio. For the same attribution criterion, the technical proposal will weigh 60%, while the bid price will have a share of 40%.
According to the description of the project, the consultant to be selected will have to ensure the high-quality supervision of the design and execution works, the proper administration of the design and execution contract, advising CFR SA on contractual problems, ensuring an adequate accounting system and registering the progress of works, assisting CFR SA in the timely planning funds, assisting CFR SA in the project management, monitoring and evaluation of the entrepreneur’s activity.


Share on:
Facebooktwitterlinkedinmail

 

RECOMMENDED EVENT: